Building permits in Senegal: the file, official fees and timelines

Starting work without authorisation exposes you to penalties and stop-work orders. Here, based on the au-senegal.com procedures portal, is the typical file and the timelines to expect. Details vary by municipality.

Slab being poured on a site managed by SLT-BTP

Where and with whom

The application is addressed to the mayor of the relevant municipality and filed with the urban planning department for the site. The legal framework rests on the Urban Planning Code (law no. 2008-43 of 20 August 2008) and the Construction Code (law no. 2009-23 of 8 July 2009).

The typical file

  • A written application addressed to the mayor.
  • A copy of the title (land title, lease, occupancy permit, certificate or surface right).
  • A location and boundary plan certified by the Land Registry survey office (Cadastre).
  • Five sets of architectural plans at 1:100: location, site plan, floor plans, section, elevation.
  • An information sheet and a descriptive estimate of the project.
  • A septic tank plan, or a statement of sewer connection.
  • The full file in 7 copies.

Fees and timelines reported

  • Urban planning tax: 1,000 to 5,000 FCFA depending on the locality, paid to the Domains collector against an assessment slip.
  • Tax stamp: 1,000 FCFA.
  • File review: up to 3 months.
  • In Dakar, the online TéléDac procedure, described as in pre-production, announces about 28 days for a simple file and 40 days for a complex one.
  • The permit must be renewed after three years if the works are not finished.

Three practical tips

  1. Have the plans drawn by an architect and check the title before spending on studies.
  2. Get the certified cadastral plan first: it is the document that takes the longest.
  3. Do not start structural works before the decision.

What the permit really costs

The reported administrative fees are modest: an urban planning tax of 1,000 to 5,000 FCFA and a tax stamp of 1,000 FCFA, so roughly 2,000 to 6,000 FCFA. The real budget sits upstream: the architect’s drawings, the certified cadastral plan, printing 7 copies and, above all, time. Budget these items separately.

A typical timeline

  1. Week 1: check the title and request the certified location plan from the Cadastre.
  2. Weeks 2 to 4: drawings, descriptive estimate and sanitation, with your architect.
  3. File the dossier in 7 copies, pay the tax and the stamp.
  4. Review: about 28 to 40 days through TéléDac in Dakar depending on the file, or up to 3 months elsewhere.
  5. Decision, then start the works.

Mistakes that cost weeks

  • A title that does not clearly prove your rights over the land.
  • A location plan that is not certified or does not match the real boundaries.
  • Drawings that ignore the zone’s designated use: first ask for an urban planning certificate.
  • An incomplete file that forces another trip to the counter.
  • Starting the foundations while waiting for the answer.

After the works

Once the site is complete, a compliance certificate serving as an occupancy permit can be requested from the authority. Check the conditions with the urban planning office before handing over the building.

Amounts and documents may differ between municipalities: confirm them with the relevant urban planning office.

Frequently asked questions

How much does a building permit cost in Senegal?

The reported administrative fees are 1,000 to 5,000 FCFA of urban planning tax and a 1,000 FCFA stamp. The main cost comes from the drawings, the certified cadastral plan and the architect, which depend on the project.

How long does it take?

File review can take up to 3 months. In Dakar, the TéléDac procedure announces about 28 days for a simple file and 40 days for a complex one.

Do I need an architect?

The file includes architectural drawings at 1:100. For most buildings, have them prepared and signed by an architect, and confirm the exact requirement with the urban planning office.

What is the risk of building without a permit?

Administrative penalties, a stop-work order and, in serious cases, demolition. An unauthorised building is also hard to finance, insure and resell.

How long is the permit valid?

It must be renewed after three years if the works are not finished.